Q1 : Which term defines the process of project compliance with policies and procedures?
A. Quality control
B. Quality assurances
C. Quality audits
D. Quality control management
The correct answer is: C .
Q2: Which process does QA provide and umbrella for?
A. Continuous process improvement
B. Quality assurance
C. Project management plan
D. Quality baseline
The correct answer is: A .
Q3: Which of the processes includes all activities of the performing organization that determines policies and responsibilites of a project?
A. Performance quality control
B. Project quality management
C. Performance plan management
D. Quality control management
Hey Everyone I have CSQA exam sample questions without answers. Can any of you provide the answers? Thanks!
Hey Everyone Here is another CSQA exam sample questions without answers. Can any of you provide the answers? Thanks!
1. Do a cause-effect analysis for high defect rate.
2. Propose a QA mentoring scheme.
Thanks in advance,
freesky
Hi,
You can discussed here regarding ISTQB exam.
If you have any queries, we will sort out wid other our members.
I am planning to give exam this year.
Thx
- 2 comments






- 450 reads




Recent comments
13 hours 38 min ago
21 hours 33 min ago
1 day 1 hour ago
3 days 16 hours ago
3 days 20 hours ago
3 days 22 hours ago
3 days 22 hours ago
4 days 2 hours ago
4 days 3 hours ago
4 days 4 hours ago