Good objective Questions with Answers.
Q1 : Which term defines the process of project compliance with policies and procedures?
A. Quality control
B. Quality assurances
C. Quality audits
D. Quality control management
The correct answer is: C .
Q2: Which process does QA provide and umbrella for?
A. Continuous process improvement
B. Quality assurance
C. Project management plan
D. Quality baseline
The correct answer is: A .
Q3: Which of the processes includes all activities of the performing organization that determines policies and responsibilites of a project?
A. Performance quality control
B. Project quality management
C. Performance plan management
D. Quality control management
The correct answer is: B .
Q4: Which of the following are negative possibilities if quality requirements are not met?
A. Overworking team members and poor product quality
B. Customer complaints and late product
C. Poor quality
D. Termination
The correct answer is: A .
Q5: Which of these terms apply to identifying quality standards and how to satisfy them?
A. Quality projections
B. Quality management
C. Quality planning
D. Quality overview
The correct answer is: C .
Q6: Which of the following definitions apply to the cost of quality?
A. Left over product
B. Total cost of all project efforts
C. Customer satisfaction
D. Redoing entire project
The correct answer is: B .








Recent comments
50 min 32 sec ago
1 hour 37 min ago
3 hours 55 min ago
6 hours 24 min ago
6 hours 26 min ago
6 hours 29 min ago
6 hours 29 min ago
6 hours 40 min ago
6 hours 41 min ago
6 hours 45 min ago