Difference between and FCA (Functional Configuration Audit) and PCA (Physical Configuratioj Audit) and how can they be performed?
Any associated checklists for conductinng these audits?
Tags:








Physical configuration audit (PCA): An audit conducted to verify that a configuration item, as built, conforms to the technical documentation that defines it
Functional configuration audit (FCA): An audit conducted to verify that the development of a configuration item has been completed satisfactorily, that the item has achieved the performance and functional characteristics specified in the functional and allocated configuration identification, and that its operational and support documents are complete and satisfactory
Checklists are as below
FCA
PCA